01
Line Optimisation
UK Dairy Packer
58% → 81%
OEE improvement
47 min
Changeover time (down from 90)
6 weeks
Time to full improvement
The Challenge
A high-volume dairy packing site was consistently achieving OEE of around 58% on its primary filling line — well below the designed capacity. Management had attributed the losses to ageing equipment, but no systematic analysis had been carried out.
Our Approach
HES Consulting conducted a structured OEE study over two production weeks, mapping all downtime events, speed losses, and quality rejects. The analysis identified a filler timing drift as the primary throughput constraint, compounded by a changeover process that had grown to nearly 90 minutes through accumulated informal practice.
The Outcome
Following targeted adjustments to the filler timing parameters and a redesigned changeover procedure with operator coaching, OEE improved from 58% to 81% within six weeks. Changeover time was reduced to 47 minutes.